X can complete a job in 36 days and Y can complete it in 45 days. Z can complete the job in z days.
Z started the job. After 28 days, X and Y joined. The
job was completed in 4 more days. Find z. ​

Respuesta :

Otras preguntas

2. Who were usually poor, unskilled laborers who had limited economic opportunities in England? * Slaves Indentured servants Aristocrats O Commoners
Select the correct answer. A student read this excerpt from an argument against school uniforms and agrees with the author. Which statement below would help th
What does -12 - (-5)=
What caused eight of John Smith's men to get sick?
Project work: Prepare SCRAP BOOK 1.Collect photographs of the great freedom fighter- Mahatma Gandhi / national movement - with a write-up. The work should get u
Write a program that reads a list of 10 integers, and outputs those integers in reverse. For coding simplicity, follow each output integer by a space, including
Which of the following is equivalent to the expression below?
This one is confusing
F.ree points for all!
A boat is able to move at 7.6 m/s in still water. If the boat is placed on the south shore of a river (water current of 3.4 m/s [SE]), and the captain wants to
good job