For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Activity duration is 4 days. Which of the following statements is true?
A) The Late Finish is 14
B) The Early Finish is 12
C) Delaying this activity by 2 days will not affect project duration
D) A and B E) A, B, and C

Respuesta :

Otras preguntas

1 The main role of Andy's art teacher in this story is to help – A resolve a conflict the main character is experiencing B create the setting in which the main
which sides and angles are congruent to each other ? which two triangles are congruent? (order of letters matter) if you don’t know do not answer
Can you please help me it’s urgent?
will give brainliest
I need help with this..please help​
A package of 500 sheets of paper has a weight of 2.6 pounds.what will be the weight of 1750 sheets of the same kind of paper
if a/c = 2, what is the value of 4b/a?
Please someone help I need this ASAP pleeasee
What was the name for the series of European meetings held in 1884-1885?
The height of a triangle is 6 inches. The area of the triangle is 45 square inches. What is the length of the triangle’s base?
good job