When a contractor is under a contractual duty to construct a building and the building is destroyed by an act of nature while it is still a work in progress, the destruction __________.

Respuesta :

imustapha180
imustapha180 imustapha180
  • 08-02-2020

Answer: the destruction will not discharge the contractor's duty to perform, but will extend the date of performance

Answer Link

Otras preguntas

What homeostatic process moves particles against a concentration gradient? A. Dynamic Equilibrium B. Passive Transport C. Osmosis D. Active Transport
What is the affirmative usted command of visitar?
780 as a percentage of 1.5
write the fraction 7/16 and 193/1000 as decimal then compare the values
evaluate four mechanisms that south african government utilize to regulate and control conamination of food product
kahulugan ng tumarok
Which is a secondary source document about the cold war?
The latest online craze is a new game, Khan on Seven. You get 1 0 0 100100 points for playing the game. In addition, you get 5 0 5050 points for each seven-le
a square that is 10cm on a side contains a circle that touches the inside the square?
What was the Rhode Island system why did many mill owners copy it
good job