Answer:
Budgeted labour cost =$8,550
Explanation:
Labour budgeted is prepared using the production budget data. This is simply because the budgeted labour hour is a function of the budgeted production units.
Budgeted labour hours = Production budget × standard hours per unit
                  =  380 × 1.5 hours=570
Budgeted labour cost= Budgeted labour hours × Standard labour rate
                    = 570  hours × $15 =$8550
Budgeted labour cost =$8,550