A and b can do a piece of work in 30 days while b and c can do the same work in 24 days and c and a in 20 days. If they all work together, in how many days will the work finish?

Respuesta :

RVADAMARAJANCHITHRA
RVADAMARAJANCHITHRA RVADAMARAJANCHITHRA
  • 06-07-2020

Answer:

16 days.

Step-by-step explanation:

The work done by a and b in one day = 1/30

The work done by b and c in one day = 1/24

The work done by c and a in one day = 1/20

Find the sum of all these fractions , this will be the work done by 2a and 2b and 2c in one day. This gives 0.125, which is equivalent to 1/8.

The work done by 2 of each person = 8, so it takes double this value for just one of each person, this is 16 days.

Hope this helps

Answer Link

Otras preguntas

Which is an arithmetic sequence? Answers: A.)1,2,4,8,16,32 B.)1,3,5,7,9 C.)1,1,2,3,5,8,13
what is the solution of stammering problem?​
1. Особливості будови клітин людини
Read the dialogue spoken by X in paragraph 114. “I’m not from another planet. I’m from here.” Based on this dialogue, what does X want people to understand? A.
This is the question that im stuck on
Cu(OH)2 + Nacl ????????????
y= 2x + 3 find f(-5)
brainliest to correct quickly
Unlike psychology, the primary focus in sociology is to study how __________ affect behavior. A. emotions B. social influences C. cognitive processes D. individ
PLEASE HELP the question is in the picture
good job