15 men can complete the construction of a wall in 12 days in how many days can 18 men complete the same work​

Respuesta :

maniknandini
maniknandini maniknandini
  • 09-11-2021

Answer:

10 days

Step-by-step explanation:

15 men -----  12 days

18 men -----    x ?

They are inversely proportional

more men less days

15 / 18  * 12 = 10 days

Answer Link

Otras preguntas

Object a has a massive 12 g in a volume of 8 cm³ object B has a mass of 20 g in a volume of eight 8 cm³ which object has a greater density and by how much objec
Martha blank tu al campo
what three issues should be considered when deciding whether a potential educational objective should be used in the grading process
if the market price is $30 and if the firm is producing output, what is the amount of its average variable cost?
a teacher wants to see if a new unit on taking square roots is helping students learn. she has five randomly selected students take a pre-test and a post test o
A suspension bridge with weight uniformly distributed along its length has twin towers that extend 100 meters above t parabolic in shape and are suspended from
What is everything I need to know about linear equations with variables on both sides?
α and β rays consist of particles, whereas γ rays are high-energy radiation and contain no particles and thus they have no mass. given that the penetrating powe
PLEASE HELPP!!! DUE NOW i need real help very simple
an electron travels through space and has a velocity uncertainty of 131 m/s. what is the minimum uncertainty in the electron's position?
good job